Chennai’s planned maintenance power cuts for Sunday, September 6, show a limited footprint. The only outage officially listed for the metro region is in Tambaram. It covers the MEPZ SEZ industrial zone from 9 am to 2 pm. Officials add, “Supply will be resumed before 2 pm, if works complete.” Core Chennai circles show no planned shutdowns as of 9:30 am. Always verify status before using lifts or critical equipment.
Shutdowns typically run between 9 am and 2 pm for maintenance crews. Longer windows are sometimes used, depending on feeder load and complexity. Plan RO water, inverter charge, and Wi‑Fi router backups in advance. Avoid lift trips near start or end of the cut. Rain or strong wind can delay work or force rescheduling. TANGEDCO often restores early when tasks finish ahead of schedule.

Chennai power shutdown area list and outage windows
| Circle | Localities and prominent streets | Outage window | Feeder/Substation tag | Restoration ETA |
|---|---|---|---|---|
| Tambaram | MEPZ SEZ industrial zone; all HT and LT services | 9:00 am–2:00 pm | MEPZ SEZ feeders (Tambaram) | Before 2:00 pm, if works finish |
| Chennai North, Central, South | No planned shutdowns listed as of 9:30 am | — | — | Monitor portal for updates |
This table reflects Sunday’s official maintenance notice and live aggregator status at publication. If your street borders Tambaram Corporation and Greater Chennai limits, confirm jurisdiction and the exact feeder tag on the portal before planning equipment downtime. Industrial units should stagger loads to avoid sudden surges when supply resumes.
How to verify today’s TANGEDCO outage status
Open the planned outage portal, select your circle, complete the captcha, and submit. Recheck after noon for restoration updates and late additions. For unplanned faults, use the CCMS public tracker to see active complaints. You can also use the TNEB Mobile App to log and track issues. For assistance, call Consumer Care at 94987 94987. You may also message the verified WhatsApp billing line 9498794987.
Expect feeders to return progressively once work clears safety checks. If showers build over Tambaram or GST Road, allow extra time for crews. Before rebooting servers or elevators, confirm supply is stable for fifteen minutes. Bookmark the outage portal and keep the CCMS page handy through the day. If in doubt, call the helpline and quote your service number.



Click it and Unblock the Notifications